ࡱ> gify[ :bjbj  G[pa!\pa!\1>JJJJJ^^^8,T^9h(>>>rrr9999999$;=C9J rr C9JJ>>4X9|%|%|% ^J>J>9|% 9|%|%q6a7> | R7( 9n909)78>!>(7>7%$<`2rrrC9C9#rrr9 >rrrrrrrrr> : SECTION 20 08 00 Fire Supression/Plumbing/HVAC Systems Commissioning GENERAL RELATED DOCUMENTS Drawings and general provisions of the Contract, including General Conditions and Division 01 Specification Sections, apply to this Section. Specifications throughout all Divisions of the Project Manual are directly applicable to this Section, and this Section is directly applicable to them. SUMMARY The purpose of this Section is to define responsibilities in the Commissioning process. Additional system testing is required within individual Specification Sections. Ensure that all systems are operating in a manner consistent with the Contract Documents. General Commissioning requirements and coordination are detailed in Division 01. Execute all Commissioning responsibilities assigned and include the cost of Commissioning in the Contract price. HVAC systems to be commissioned include the following: [Edit or add to the following scope as appropriate to the Project.] Chilled Water Systems Cooling Tower Hot Water and Steam PRV Station Steam Boiler System Pumps Heat Exchangers Air Handling Units Fans Piping Systems Ductwork Systems Fire, Fire/Smoke and Volume Dampers Chemical Treatment Roof Top Packaged DX Units Split Systems Fan Coil Units Terminal Units Unit Heaters Building Automation System Plumbing Systems to be commissioned include the following: Sanitary Waste and Vent Roof and Storm Drainage Laboratory (Chemical) Waste and Vent Grease/Oil Laden Waste and Vent Sump/Ejector Pumps Domestic Water Booster Pumps Domestic Water Storage/Break Tank Water Softeners Pure Water Production Equipment (R.O., D.I., etc.) Domestic Water Heaters Domestic Hot Water Circulating Pumps Domestic Cold Water Distribution Domestic Hot Water Distribution Natural Gas Distribution Medical Air Compressors and Vacuum Pumps Laboratory Air Compressors And Vacuum Pumps Medical Compressed Gas Cylinder Manifolds Laboratory Compressed Gas Manifolds Medical Gas and Vacuum System Alarms Laboratory Gas and Vacuum System Alarms Medical Gas and Vacuum Distribution Laboratory Gas and Vacuum Distribution Plumbing Fixtures Plumbing Systems/Emergency Power Source Integration Plumbing Systems/Building Automation System Integration Fire Protection Systems to be commissioned include the following: Fire Pump Wet Standpipe Wet Fire Sprinkler Dry Fire Sprinkler Pre-Action Fire Sprinkler Chemical Fire Suppression Fire Protection Water Storage/Break Tank Fire Protection Systems/Emergency Power Source Integration Fire Protection Systems/Fire Alarm System Integration Fire Water Tank and piping system including valves, high/low level, over flow, metering, basin and circulation loop. REFERENCE STANDARDS The latest published edition of a reference shall be applicable to this Project unless identified by a specific edition date. All reference amendments adopted prior to the effective date of this Contract shall be applicable to this Project. All materials, installation and workmanship shall comply with all applicable requirements and standards. definitions Refer to Specification Section 01 91 00 General Commissioning Requirements for definitions. SUBMITTALS Contractor shall prepare Prefunctional Checklists and Functional Performance Test (FPT) procedures and execute and document results. All Prefunctional Checklists and tests must be documented using specific, procedural forms in Microsoft Word or Excel software developed for that purpose. Prior to testing, Contractor shall submit those forms to the Owner for review and approval. Contractor shall provide Owner with documentation required for Commissioning Work. At minimum, documentation shall include: Detailed Start-up procedures, full sequences of operation, Operating and Maintenance data, performance data, Functional Performance Test Procedures, control drawings, and details of Owner-contracted tests. Contractor shall submit to Owner installation and checkout materials actually shipped inside equipment and actual field checkout sheet forms used by factory or field technicians. Contractor shall review and approve other relative documentation for impact on FPTs of the systems: Shop drawings and product submittal data related to systems or equipment to be commissioned. The Subcontractor responsible for the FPT shall review and incorporate comments from the Owner and A/E via the Contractor. Incorporate manufacturers Start-up procedures with Prefunctional checklists. Draft Test, Adjust and Balance (TAB) Reports: Review and provide comments to Owner. Factory Performance Test Reports: Review and compile all factory performance data to assure that the data is complete prior to executing the FPTs. Completed equipment Start-up certification forms along with the manufacturers field or factory performance and Start-up test documentation: Subcontractor performing the test will review the documentation prior to commencing with the scheduled FPTs. Owner may require that system one-line diagrams and applicable Specification Section(s) be attached to the FPT documentation. Final TAB Reports: Subcontractor performing the test will review the documentation prior to commencing with the scheduled FPTs. Operating and Maintenance (O&M) information per requirements of the Technical Specifications and Division 01 requirements: To validate adequacy and completeness of the FPT, the Contractor shall ensure that the O&M manual content, marked-up record Drawings and Specifications, component submittal drawings, and other pertinent documents are available at the Project Site for review. PRODUCTS GENERAL All materials shall meet or exceed all applicable referenced standards, federal, state and local requirements, and conform to codes and ordinances of authorities having jurisdiction. TEST EQUIPMENT Provide all specialized tools, test equipment and instruments required to execute Start-up, checkout, and testing of equipment. Refer to Specification Section 01 91 00 General Commissioning Requirements. EXECUTION PREPARATION Construction Phase: In each purchase order or subcontract that is written for changes in scope, include the following requirements for submittal data, Commissioning documentation, testing assistance, Operating and Maintenance (O&M) data, and training, as a minimum. Attend Pre-Commissioning Meeting(s), Pre-Installation Meeting(s), and other Project meetings scheduled by the Contractor to facilitate the Commissioning process. Provide manufacturers data sheets and shop drawing submittals of equipment. Provide additional requested documentation to the Contractor, prior to O&M manual submittals, for development of Prefunctional Checklist and Functional Performance Tests procedures. Typically, this will include detailed manufacturers installation and Start-up, operating, troubleshooting and maintenance procedures, full details of any Owner-contracted tests, full factory testing reports, if any, and full warranty information, including all responsibilities of the Owner to keep the warranty in force clearly identified. In addition, the installation, Start-up, and checkout materials that are actually shipped inside the equipment and the actual field checkout sheet forms to be used by the factory or field technicians shall be submitted to the Contractor. This information and data request may be made prior to normal submittals. With input from the BAS Provider and A/E, Clarify the operation and control of commissioned equipment in areas where the Specifications, BAS control drawings, or equipment documentation are not sufficient for writing detailed test procedures. Prepare the specific Functional Performance Test procedures specified in Section 20 08 16. Ensure that Functional Performance Test procedures address feasibility, safety, and equipment protection and provide necessary written alarm limits to be used during the tests. Develop the Commissioning Plan using manufacturers Start-up procedures and the Prefunctional Checklists. Submit manufacturers detailed Start-up procedures and the Commissioning Plan and procedures and other requested equipment documentation to Owner for review. During the Start-up and initial checkout process, execute and document related portions of the Prefunctional Checklists for all commissioned equipment. Perform and clearly document all completed Prefunctional Checklists and Start-up procedures. Provide a copy to the Owner prior to the Functional Performance Test. Address current A/E and Owner punch list items before Functional Performance Tests. Air and water test, adjust and balance shall be completed with discrepancies and problems remedied before Functional Performance Tests of the respective air or water related systems are executed. Provide skilled technicians to execute starting of equipment and to assist in execution of Functional Performance Tests. Ensure that they are available and present during the agreed-upon schedules and for a sufficient duration to complete the necessary tests, adjustments, and problem solving. Correct deficiencies (differences between specified and observed performance) as interpreted by the Owners Project Manager and A/E and retest the system and equipment. Compile all Commissioning records and documentation to be included in a Commissioning and Closeout Manual. Prepare O&M manuals according to the Contract Documents, including clarifying and updating the original sequences of operation to actual conditions. During construction, maintain Record Drawings and Specifications of all Contract Documents and Contractor-generated coordination Drawings. Update after completion of Commissioning activities (include deferred tests). The Record Drawings and Specifications shall be delivered to the Owner both in electronic format as required by the Owner. Provide training of the Owners operating personnel as specified. Coordinate with equipment manufacturers to determine specific requirements to maintain the validity of the warranty. Warranty Phase: Execute seasonal or deferred tests, witnessed by the Owner, according to the Specifications. Complete deferred tests as part of this Contract during the Warranty Period. Schedule this activity with Owner. Perform tests and document and correct deficiencies. Owner may observe the tests and review and approve test documentation and deficiency corrections. If any check or test cannot be completed prior to Substantial Completion due to the building structure, required occupancy condition, or other condition, execution of such test may be delayed to later in the Warranty Period, upon approval of the Owner. Contractor shall reschedule and conduct these unforeseen deferred tests in the same manner as deferred tests. Correct deficiencies and make necessary adjustments to O&M manuals, Commissioning documentation, and Record Drawings for applicable issues identified in any seasonal testing. testing Prefunctional Checklists and Start-up: Follow the Start-up and initial checkout procedures listed in this Section and in Division 01. Start-up and complete systems and sub-systems so they are fully functional, meeting the requirements of the Contract Documents. Prefunctional Checklists shall be complete prior to commencement of a Functional Performance test. Functional Performance Tests: Functional Performance Tests are conducted after system Start-up and checkout is satisfactorily completed. Air balancing and water balancing shall be completed before Functional Performance Tests. Coordination Between Testing Parties: Factory Start-ups: Factory Start-ups are specified for certain equipment. Factory Start-ups generally are Start-up related activities that will be reviewed and checked prior to Functional Performance Tests. All costs associated with factory Start-ups shall be included with the contract price unless otherwise noted. Notify the Commissioning Team of the factory Start-up schedule and coordinate these factory Start-ups with witnessing parties. The Commissioning Team members may witness these Start-ups at their discretion. Independent Testing Agencies: For systems that specify testing by an independent testing agency, the cost of the test shall be included in the Contract price unless otherwise noted. Testing performed by independent agencies may cover aspects required in the Prefunctional Checklists, Start-ups, and Functional Performance Tests. Coordinate with the independent testing agency so that Owner and/or A/E can witness the test to ensure that applicable aspects of the test meet requirements. TRAINING Refer Specification Section 01 79 00 Demonstration and Training. END OF SECTION 20 08 00   MD ANDERSON Project No. XX-XXXXMD Anderson project nameA/E NameIssue DescriptionA/E Project No.Month, 00, 0000 鶹ӳ Fire Supression/Plumbing/HVAC Systems CommissioningMD Anderson Cancer Center20 08 00 MS052616 PAGE 1 of  NUMPAGES 7 "178<=FPbc < = > K L [ ` a r ncf<նh)qhkX hRhRhnh ThYyhgqhobhh6hhohhh;u h~ h ph ph~ThhIoh2EGPc = [  . 5 E X ] l } $ gdobgdYygdD$ ` y +;o.Z@R gdobgdD /C]wdefq;S,zgdkXgdkXgdkX  & F8^8gd: VgdRgdDgdob<=mnvwxyc~? %%((=)@)E*F*l+m+++-ѿѸٰ谣h'h^JhHdlhhU4 hJdhJdhh hRshRs h~ h phRsh+h p hkXhkXhgqhk8h)qh=hUhkXh)i ?zdb? S!!W"#$$%&'gdgdgdgdHdlgdJdgdRsgdDgdkX'(-)F*m+,,-l..#/3//022223)4G4 535E7/9gdDgdFsgdkPogdDgdDgdgdgd- -4-:-W-Y--------- . .////j1k1s1t1k2q2r2s222G4 52535O5P55555'6(6t6u66666%7&77788-9.9/97989>9?9@9B9G9K9L9T9¾h+hC'hCG he`^he`^he`^h Thca hjVehjVehk8h BhjVe hDhDhFshkPohDh)i hUh_BhhXsB/989{999999999999999999999999999gde`^gd TT9]9z9{99999999999999999:::: :/:1:2:3:4:K:M:\:j:q:r:v:w::::::::::::::::콹쩥왎hXsmHnHu*jh pUhXsh: Vh`1h2hcVh*hhIohN=hnhDuhk8 hDuhDuhSh:3hgjhgUh ph ThHdlh+hC'4999999999999999: $$Ifa$Kkd$$IfTH0x$`64 HaT $$Ifa$$If:: :0:1:2:3:4:M:ZXVVKkd$$IfTH0x$`64 HaT $$Ifa$$IfKkd_$$IfTH0x$`64 HaTM::::::::`W $IfgdXsGkd~$$IfHU0$ $ $4 Hal$IfGkd$$IfHU0$ $ $4 Hal $$Ifa$:::::::::::hghXsmHnHu*jh pUh pjh pU* ::::::Gkd$$IfHU0$ $ &$4 HalE....()()))()000?P&P/R 8$BP/ =!"#8$% Dp]$$If!vh#v#v`:V H655`44 HT]$$If!vh#v#v`:V H655`44 HT]$$If!vh#v#v`:V H655`44 HT_$$Ifl!vh#v #v:V HU$5 544 Hal_$$Ifl!vh#v #v:V HU$5 544 Halk$$Ifl!vh#v #v:V HU$,5 5944 Hal&s2 0@P`p2( 0@P`p 0@P`p 0@P`p 0@P`p 0@P`p 0@P`p8XV~ 0@ 0@ 0@ 0@ 0@ 0@ 0@ 0@ 0@ 0@ 0@ 0@ 0@ 0@_HmH nH sH tH J`J Normal1$OJQJ\]_HmH sH tH ZZ  Heading 1$ <@&^ ;CJKH \^JaJ RR  Heading 2$ P 1$@&^  5;CJXX  Heading 3$ h!  1$@&^ 5;mH sH PP U4 Heading 4$<@&5CJOJQJaJDA D Default Paragraph FontVi@V  Table Normal :V 44 la (k (No List P+@P Endnote Text,EOS$1$a$5;.. TOC 9 ^P@P Footnote Text,Foot Title;F>"F h6Title $1$a$5CJOJQJ\]R@2R Header,Head Project  !;4 B4 Footer  !BOB PRT$$ & F1$a$5,b, TITLE5;POrP DPR10$$ & F `81$^8`a$XOrX ART3$$ & F `01$^`0a$;LOL PR2($$ & F 1$`a$\TOT PR30$$ & F 1$^`a$\TT PR40$$ & F  p1$^p`a$\TT PR50$$ & F `  1$^ `a$\2O2 CMT $1$5;^^ h6Spec Heading 1r & F1$CJOJQJ\]aJ:: RsNorm1$CJOJQJ\]^^ RsSpec Heading 3r! & F1$CJOJQJ\]aJf"f RsSpec Heading 2r" & F01$]0CJOJQJ\]aJX2X U4 ListClos_In-5#P1$^`POJQJ\]HRH ' Balloon Text%CJOJQJ^JaJPK![Content_Types].xmlN0EH-J@%ǎǢ|ș$زULTB l,3;rØJB+$G]7O٭VvnB`2ǃ,!"E3p#9GQd; H xuv 0F[,F᚜K sO'3w #vfSVbsؠyX p5veuw 1z@ l,i!b I jZ2|9L$Z15xl.(zm${d:\@'23œln$^-@^i?D&|#td!6lġB"&63yy@t!HjpU*yeXry3~{s:FXI O5Y[Y!}S˪.7bd|n]671. tn/w/+[t6}PsںsL. J;̊iN $AI)t2 Lmx:(}\-i*xQCJuWl'QyI@ھ m2DBAR4 w¢naQ`ԲɁ W=0#xBdT/.3-F>bYL%׭˓KK 6HhfPQ=h)GBms]_Ԡ'CZѨys v@c])h7Jهic?FS.NP$ e&\Ӏ+I "'%QÕ@c![paAV.9Hd<ӮHVX*%A{Yr Aբ pxSL9":3U5U NC(p%u@;[d`4)]t#9M4W=P5*f̰lk<_X-C wT%Ժ}B% Y,] A̠&oʰŨ; \lc`|,bUvPK! ѐ'theme/theme/_rels/themeManager.xml.relsM 0wooӺ&݈Э5 6?$Q ,.aic21h:qm@RN;d`o7gK(M&$R(.1r'JЊT8V"AȻHu}|$b{P8g/]QAsم(#L[PK-![Content_Types].xmlPK-!֧6 0_rels/.relsPK-!kytheme/theme/themeManager.xmlPK-!R%theme/theme/theme1.xmlPK-! ѐ' theme/theme/_rels/themeManager.xml.relsPK] 2"'===<-T9::"%'+$ z'/99:M::: !#$&()*,$&+68@!tt@ @H 0(  0(  B S  ?B C D E F G H 8282F2222B2K2K2222=*urn:schemas-microsoft-com:office:smarttags PlaceName9*urn:schemas-microsoft-com:office:smarttagsplace:*urn:schemas-microsoft-com:office:smarttagsStreet8*urn:schemas-microsoft-com:office:smarttagsCity q1y111111111111221111111111122"178<=`a c d d e e ? =!@!##% %4%:%%%%% & &R&R&k*q*r*s***0081z1{1{11111113242K2M22222222222222222 d e e  =!@!##% %4%:%%%%% & &R&R&k*q*r*s***0081z1{1{11111111111111111111111111222 2/2222222*2{<+>;* w4܎lK8"e/ %!4hDnAa^`o( PART - ^`o( SCHEDULE  - ^`o(PRODUCT DATA SHEET  - ``^``o(.``^``o(.^`o(.^`o(.  ^ `o()` ` ^` `o()0^`0o(1..808^8`0o(1...xXx^x`Xo(1....   ^ `o( 1.....   ^ `o( 1...... `^``o(1....... ^`o(1........ HH^H`o(1......... @h@^@`ho(1..........^`o(.0^`0o(2..808^8`0o(2...xXx^x`Xo(2....   ^ `o( 2.....   ^ `o( 2...... `^``o(2....... ^`o(2........ HH^H`o(2......... @h@^@`ho(2..........0^`0o(3..808^8`0o(3...xXx^x`Xo(3....   ^ `o( 3.....   ^ `o( 3...... `^``o(3....... ^`o(3........ HH^H`o(3......... @h@^@`ho(3..........$ ^`o(hH.$ ^`hH.$ L^`LhH.$ ^`hH.$ TT^T`hH.$ $ L$ ^$ `LhH.$   ^ `hH.$ ^`hH.$ L^`LhH.N^`No(fNf^f`No(.808^8`0o(..0^`0o(... ^`o( .... ^`o( .....  ` ^ ``o( ......  ` ^ ``o(.......   ^ `o(........{<+we/lnA4 MASTERSPECdc`1'_B; )i Sw=U4k8+Rca n#!#H& 12h68B:O> B,CMNCK]N!EP T+T~T: V Xl[ .^e`^d`ob RcJdjVeTzkHdlnnkPo prFsRsXsDu;u{P|}m&~ Yygq*Io2+3Rg)q*q(tAhocVhkXN=CG"_kS%&h\*gNC'0'DU72SH:3R11@z1z1z1z12@UnknownG*Ax Times New Roman5Symbol3. *Cx Arial9Palatino5. .[`)TahomaA$BCambria Math"9)hEEGf-*Yf-*Y!)P4z1z12q)PHP ?22!xx 9Fire Suppression, Plumbing and HVAC Systems CommissioningDOSpain Spain,David O(       Oh+'0`     ( 4@HPX<Fire Suppression, Plumbing and HVAC Systems CommissioningDOSpainALTERATION OF THIS OFFICIAL DOCUMENT IS PROHIBITED WITHOUT EXPRESS WRITTEN PERMISSION BY OFFICE OF CAPITAL PLANNING AND MANAGEMENT AT UT MD ANDERSON CANCER CENTER. Normal.dotmSpain,David O2Microsoft Office Word@@@3c*@\Z@\Zf-* ?@ABCDEFGHIJKLMNOPQRSTUWXYZ[\]_`abcderhknlmopqstuvwxz{|}~Root Entry Fp;jData .1Table6>WordDocumentG[SummaryInformation(VDocumentSummaryInformation8,DCompObjrMsoDataStore p;p;  !"#$%&'()*+5-./01234;689:<=>?  F Microsoft Word 97-2003 Document MSWordDocWord.Document.89q ds:itemID="{005384B1-FF06-4B7A-835B-534DF9F67579}" xml4DTH2IGM0IKL0Q==2 p;p;Item  ^x.PropertiesYRTAA14DWNN5Z4Q==2 p;p;Item  Properties35QG4UDJSA==2p;p;Item  PropertiesW4QUSWLOA==2p;p;Item eProperties7 w>7BD-A501-4787-AA50-327FA28FA648}" xmlDocumentLibraryFormDocumentLibraryFormDocumentLibraryForm">Document ID Generat 1000MicrosofDocument ID GeneratorSynchronous100011000Microsoft.Office.DocumentManagement, Version=14.0.0.0, Culture=neutral, PublicKeyToken=71e9bce111e9429cMicrosoft.Office.DocumentManagement.Internal.DocIdHandlerDocument ID GeneratorSynchronous100021001Microsoft.Office.DocumentManagement, Version=14.0.0.0, Culture=neutral, PublicKeyToken=71e9bce111e9429cMicrosoft.Office.DocumentManagement.Internal.DocIdHandlerDocument ID GeneratorSynchronous100041002Microsoft.Office.DocumentManagement, Version=14.0.0.0, Culture=neutral, PublicKeyToken=71e9bce111e9429cMicrosoft.Office.DocumentManagement.Internal.DocIdHandlerDocument ID Generator This value indicates the number of saves or revisions. The application is responsible for updating this value after each revision. " minOccurs="0" maxOccurs="1" type="xsd:string"> ociationName" type="xs:string"> me>Synchronous100061003Microsoft.Office.DocumentManagement, Version=14.0.0.0, Culture=neutral, PublicKeyToken=71e9bce111e9429cMicrosoft.Office.Docu՜.+,D՜.+,l px   N CAPITAL PLANNING AND MANAGEMENT UT MD ANDERSON CANCER CENTERYz1 :Fire Suppression, Plumbing and HVAC Systems Commissioning Title@H8`Status Published Date to ExtementManagement.Internal.DocIdHandler/metadata/longProperties"/>